Method of Application
Should be applied with an appropriate brush, trowel or spraying machine in a minimum of 2 layers. In order to apply the second layer, the first layer needs to finish drying first.
The second layer should be applied perpendicular to the first layer.
It is recommended to use waterproofing mesh or seal between the layers in order to improve the carrying capacity of the product.
Until through-dry state is achieved the foundation pit should not be closed. After the cover is protected with the appropriate thermal insulation and drainage plates, a filler application should be applied as well.
The tools used should be rinsed off with water before they dry. In case the material on the tools have already dried, solvent can be used in order to clean them.